By Max Winter-Leinweber9 min read

In short

Sprints in agile development produce working software every week or two. The MVP is the point where that software is first worth handing to real users, because it covers one whole job they can finish without you. It usually takes several sprints to get there, and once it's live, what users do sets the order of everything left on the backlog.

MVP is
A product decision: what to release
Agile is
A delivery method: how to build it
Worked example
A waiting list for an allotment society
Common mistake
Calling every sprint's output an MVP

What is an MVP in agile development?

It's the first release that people outside the team can rely on, after a run of sprints that only the team has used. Until then, the work is judged by the team and whoever watches the demos. From then on, it's judged by whether users come back.

The two ideas come from different places. The Agile Manifesto, written in 2001, never mentions a minimum viable product; Eric Ries and the lean startup movement made the term popular later. They sit together easily because of one of the manifesto's principles, that working software is the primary measure of progress. An MVP applies that principle to the whole product, and raises the bar: the measure becomes whether strangers use it.

How is an MVP different from a sprint increment or a release?

Increments and releases describe how software moves from the team to users. The MVP is a judgement about what's in it: the first release that covers a whole job.

Five agile and product terms compared by what each one is, who decides it and how often it happens
TermWhat it isWho decidesHow often
SprintA fixed block of time, often one or two weeks, with one goalThe team, with the product ownerBack to back, all through the build
IncrementWorking, tested software added during a sprintThe team, against its definition of doneAt least once a sprint
ReleaseIncrements made available to usersThe product ownerWhenever the increments are worth using
MVPThe first release that lets real users finish the core job aloneThe founder or product ownerOnce, at the start
BacklogThe ordered list of work still to doThe product ownerReordered every sprint

The Scrum Guide, the most widely used description of how agile teams run sprints, doesn't define an MVP, so every team fills the gap its own way. Write down what yours is, in one sentence, before the first sprint starts.

Is every sprint's output an MVP?

No. Each increment should be finished to a standard you could release, but one increment rarely covers a whole job. Sign-in that works, with nothing to do after signing in, is a good increment and a useless release.

A bridge of three sprint spans, offer sent, reply or lapse and list imported, that only reaches the MVP release together.

The opposite mistake is treating the MVP as phase one of a long plan, and building it in sprints that nobody outside the team sees until month six. That's a fixed plan delivered in fortnightly chunks. It throws away the reason to build an MVP at all, which is to learn from real use early.

The increments add up to an MVP once one kind of user can get from the start of the job to the end on their own, with their data saved and kept private. Our explainer on MVP software turns that moment into five checks you can run. Run the five checks for MVP software.

Where do you draw the MVP line on a backlog?

Lay the job out as a row of steps, put the stories for each step underneath, and draw a line across. Everything above the line is the MVP. Everything below waits until users have told you something. This is user story mapping, popularised by Jeff Patton, and it stops a backlog from becoming a flat list where every item looks equally urgent.

A story map of sticky notes: five steps along the top, one story under each above a strip of MVP tape, the rest below.

Take an allotment society with eighty people on its waiting list and plots that come free a few times a year. Today the secretary works through a spreadsheet, emails whoever is next and chases them for an answer. The one job is getting a vacant plot taken up by the next person in line.

  1. Write the bet. If offers go out automatically and lapse after a week, vacant plots are taken up faster and the secretary stops chasing. The measure is how many days a plot stays vacant before someone accepts it.

  2. Map the steps. Someone joins the list, a plot falls vacant, an offer goes out, the offer is answered and the plot is handed over.

  3. Draw the line. Keep the stories that let one person move through every step, and move the rest below.

  4. Mark the manual steps. Anything a person can keep doing by hand for the first few months, such as collecting rent, stays manual.

  5. Set the definition of done. Make it cover what viable means here: each member sees only their own place on the list, and errors reach someone who will act on them.

The allotment society's stories above and below the MVP line, with the reason each one is placed where it is
StoryAbove or below the lineWhy
A resident joins the waiting list and sees their positionAboveThe first step of the job
The secretary marks a plot as vacantAboveStarts every offer
The next person gets an email offer with accept and decline linksAboveThe step the secretary spends most time on today
An unanswered offer passes to the next person after seven daysAboveRemoves the chasing, which is the bet
The secretary sees who holds each plot and who is nextAboveNeeded to run the list without the spreadsheet
Annual rent invoices and paymentBelowCollected by bank transfer today, and that can carry on
A map of the site with each plot markedBelowNice to have; the plot numbers already work
Text message remindersBelowWait to see whether email offers go unanswered
Plot inspection notesBelowA separate job for a different committee member

Five stories is a small MVP, which is the point. If your own list won't shrink that far, the free MVP Scope Planner lets you size each feature and shows which ones fit a first release, which can wait and which package they match. Draw your own line with the MVP Scope Planner.

How many sprints does it take to build an MVP?

A focused MVP usually takes between one and four sprints of one or two weeks each. Give each sprint a goal that moves a user one step further through the job, and judge the sprint by whether that step works.

The allotment society MVP as three one-week sprints, with each sprint's goal and what is shown at the end
SprintSprint goalShown at the end
OneA plot can go from vacant to offeredThe secretary marks a test plot vacant and the next person gets the email
TwoAn offer can be answered or lapseA tester accepts one offer, ignores another, and the second passes on after the set time
ThreeThe secretary can run the list aloneThe real waiting list imported, with positions checked against the spreadsheet

Stop after any of these sprints and you'd still have working software for the steps covered so far, which is what makes the plan safe to change halfway. Our week by week guide covers the scoping, design and launch weeks either side of the build. How to build an MVP, week by week.

Which agile habits help an MVP, and which get in the way?

Keep the habits that shorten feedback. Scale the rest down to fit a team of two or three, because most agile practice was written for bigger teams working on products that already exist.

Worth keeping

  • A product owner, often the founder, who decides what goes above the line and can turn down anything that doesn't serve the job.

  • A demo at the end of each sprint for someone who has the problem. The allotment secretary will spot a missing step that a developer reading the stories won't.

  • Private, safely saved data and reported errors written into the definition of done from the first sprint, so there's nothing to bolt on at the end.

  • A fifteen-minute retrospective. For a small team that's long enough to find what slowed the sprint down.

Worth scaling down

  • Velocity targets. Points completed say nothing about whether users want the product; the bet you wrote down does.

  • Estimating the whole backlog. Most stories below the line will change or vanish once users arrive, so estimate each one when it moves up.

  • Separate planning, refinement and review meetings every week, which can cost a team of two a day it doesn't have.

  • Putting off fixes that touch data until the next sprint. A rough screen can wait; members seeing each other's details can't.

What happens to the backlog after the MVP ships?

The stories below the line get reordered against what users actually did, and some get deleted. The sprint rhythm carries on as before. What changes is where each sprint's goal comes from: before launch it came from the story map, and after launch it comes from the measure you chose.

For the allotment society, the measure is days from a plot falling vacant to an offer being accepted. If offers are accepted within two days, the bet held, and the next sprint can go on the rent invoices the treasurer keeps asking for. If most offers lapse unanswered, the problem is reaching people, and text message reminders jump from below the line to the top.

  • The measure you chose is recorded from the first day.

  • Someone reads it, along with what users say, before each sprint is planned.

  • Every story below the line is reordered against that evidence.

  • Anything users are working around by hand is a candidate for the next sprint.

The first item only works if the measure is wired up before launch, on the same launch list as the legal pages and payments. The free App Launch Checklist builds that list for your app from five questions. Build your list with the App Launch Checklist.

Can an MVP be built in a fixed-price sprint?

Yes, once the scope is fixed. Agile normally holds time and cost steady and lets scope move. A fixed price works when the MVP line is drawn before the sprint starts and nothing from below it creeps in.

For a rough idea of what the stories above your line add up to, the free MVP Cost Calculator asks eight questions about your app and gives an estimate in development weeks and pounds, along with what drives the price. Estimate your build with the MVP Cost Calculator.

That's how we work: we agree the scope up front, then build it in a fixed-price sprint of £7,500 + VAT for two weeks or £15,000 + VAT for three. Each includes a week of changes from your feedback and a handover week after launch, and the code is in your name. See our MVP development services and what each package includes.

Frequently asked questions

Should you use Scrum or Kanban for an MVP?
Either works. Scrum's fixed sprints give a small team a regular deadline and a demo to aim at, which suits a build with a launch date. Kanban has no sprints: the team picks up the next card whenever one is finished, which suits a single developer, or the months after launch, when work arrives as a steady trickle of user feedback.
What is the difference between an MVP and a minimum marketable feature?
An MVP is a whole first product released to test whether people want it. A minimum marketable feature is the smallest piece of new functionality worth releasing to customers who already use a product. The MVP comes first; minimum marketable features are how many teams plan the releases after it.
Portrait of Max Winter-Leinweber

About the author

Max Winter-Leinweber

Founder, Scryptic

Max is the founder of Scryptic and a full-stack developer with five years of experience building software for enterprise clients and startups. He builds MVPs for UK founders and takes apps made with no-code and AI builders through to production.

Planning an app?

Tell us what you want to build on a free call, then get a written estimate.

Book a discovery callHow our MVP development works